West Lakes Gardens First Addition Drainage Improvement

Project Quick Facts

  • Estimated Completion: March 2024
  • Construction Cost: $1,596,420
  • Project Manager: Anaily Padron, P.E.
  • Project Contractor: ATC Engineering, Inc
Overview

The West Lakes Gardens First Addition Drainage Improvement project is part of the Town’s comprehensive plan to mitigate flooding. The project consists of drainage system improvements on NW 153rd Terrace and NW 152nd Terrace between 87th and 89th Avenues.

Details

The stormwater project will include the addition of catch basins, French drains, manholes, valley gutters as well as restoration and resurfacing of the existing roadway surface, and new pavement markings. Once complete, the new system will increase stormwater management capacity and is intended to mitigate flooding in the area.

Funding Source

The West Lakes Gardens First Addition Drainage Improvement Project is funded through the Stormwater Utility System Revenue Bonds Series 2021.

Contact

Thank you for your patience and cooperation as we strive to continue Growing Beautifully.

Project Manager:

Anaily Padron, Capital Improvement Project Manager

E: padrona@miamilakes-fl.gov

O: (305) 512-7133